Bases vs. asset weather files

You can add weather to bases and assets within your cases.

Which weather file is used during the simulation to determine downtime depends on the logistic and either the weather criteria or process step being simulated.

Construction

Crew transfer vessel

Weather criteriaWeather file
Significant wave height access limitAsset
Visibility access limitAsset

Heavy lift vessel

Process stepWeather file
MobilisingBase
LoadoutBase
Transit to wind farmAsset
Jacking upAsset
InstallationAsset
Jacking downAsset
Transit to next assetAsset
Transit from wind farmAsset
Arrival at baseBase

Service operation vessel

Weather criteriaWeather file
Significant wave height access limitAsset
Visibility access limitAsset
Wind speed access limitAsset

Helicopter

Weather criteriaWeather file
Wind speed access limitAsset
Visibility access limitAsset
Significant wave height access limitAsset

Cable installation vessel

Process stepWeather file
MobilisingBase
LoadoutBase
Transit to wind farmAsset
Cable layingAsset
Cable burialAsset
Transit to next assetAsset
Transit from wind farmAsset
Arrival at baseBase

Towing vessel

Process stepWeather file
MobilisingBase
LoadoutBase
Towing to wind farmAsset
Wind turbine hook upAsset
Transit from wind farmAsset
Arrival at baseBase

Crane

Process stepWeather file
MobilisingBase
Transit to turbineAsset
Pre-assemblyAsset
Transit from turbineAsset
Arrival at baseBase

Anchor-handling vessel

Process stepWeather file
MobilisingBase
LoadoutBase
Moving to wind farmAsset
InstallationAsset
Cable layingAsset
Cable burialAsset
Transit from wind farmAsset
Arrival at baseBase

Heavy transport vessel / feeder/ barge

Process stepWeather file
MobilisingBase
LoadoutBase
Transit to wind farmAsset
Jacking upAsset
InstallationAsset
Jacking downAsset
Transit to next assetAsset
Transit from wind farmAsset
Arrival at baseBase

Component transfer vessel

Process stepWeather file
MobilisingLoadout base
LoadoutLoadout base
Transit to loadoff baseAsset or loadoff base
LoadoffAsset or loadoff base
Transit back to loadout baseAsset or loadoff base
Arrival at loadout baseLoadout base

O&M

Crew transfer vsesel

Weather criteriaWeather file
Significant wave height access limitAsset
Lowest tideBase

Heavy lift vessel

Weather criteriaWeather file
Significant wave height jacking limitAsset
Wind speed crane operation limitAsset
Wind speed limitation reference heightAsset
Lowest tideAsset
MobilisingBase
DemobilisingBase
LoadoutBase

Service operation vessel

Weather criteriaWeather file
Significant wave height access limitAsset
Wind speed access limitAsset
Wind speed limitation reference heightAsset
Lowest tideAsset

Helicopter

Weather criteriaWeather file
Wind speed access limitAsset
Wind speed limitation reference heightAsset
Visibility access limitAsset
Significant wave height access limitAsset

Towing vessel

Process stepWeather file
Mobilising towing inBase
Transit to assetAsset
DisconnectAsset
Tow to portAsset
Tow to wind farmAsset
Preparation for work at portBase
Demobilisation towing inBase
Mobilisation towing outBase
Preparation for work towing outAsset
HookupAsset
Transit to next assetAsset
Transit to portBase
Demobilisation towing outBase

Crane

Weather criteriaWeather file
Wind speed limit crane operationBase
Wind speed limitation reference heightBase